For sitework & earthwork estimators

Sitework takeoff, cut and fill from the grading plan.

Click the spot elevations on the grading plan and Kisheet reads them as existing and proposed grade, with cut and fill for any area. Paving, curb, pipe and erosion control come off the same sheets.

Step by step

A sitework bid in Kisheet, step by step.

A grading and drainage plan for a branch bank pad: a parking lot draining to a valley, a drive-through lane, curbs, three inlets and a storm line to the street. Here is how it goes to cut and fill, paving, curb and pipe.

The drawings are a sample set made for this guide. Every picture is a real screenshot of Kisheet, pre-release build of October 21, 2026.

  1. 1

    Make the site tools

    Kisheet reads the 1" = 20' scale printed under the plan. One list makes the tools: the limits of grading and the asphalt as areas, curb and each pipe size as runs, the inlets as a count.

    Tools › Measure › Use Printed Scale; Tools › Tool Sets › New Tool Set from Excel or CSV

    The Sitework tool set in the tool palette beside the grading and drainage plan
    Kisheet, October 21, 2026
  2. 2

    Existing ground from the survey spots

    Turn on Existing Grade Spots and click each surveyed elevation on the plan. Kisheet reads the printed number under the click, so nothing is typed, and marks each spot.

    Tools › Measure › Earthwork › Existing Grade Spots, then click each printed elevation

    The existing survey spot elevations marked on the grading plan
    Kisheet, October 21, 2026
  3. 3

    Proposed grade from the design spots

    Then Proposed Grade Spots: click the top of pavement, sidewalk, finished floor and finished grade spots, and the match-existing spots along the limits of grading where the new grade ties back in.

    Tools › Measure › Earthwork › Proposed Grade Spots, then click each printed elevation

    The proposed spot elevations marked on the grading plan beside the existing ones
    Kisheet, October 21, 2026
  4. 4

    Cut and fill inside the limits of grading

    Trace the limits of grading as an area and choose Cut and Fill for the Selected Area. Kisheet compares the two grounds over it and gives the cut and fill in cubic yards, and puts them in the takeoff table.

    Draw the area, then Tools › Measure › Earthwork › Cut and Fill for the Selected Area

    The limits of grading traced on the plan, with the cut and fill in cubic yards in the message bar
    Kisheet, October 21, 2026
  5. 5

    Paving, curb and storm pipe

    Click the four corners of the parking lot for its asphalt, trace the curb round the lot and the island, then each storm pipe with the tool for its size and material, and count the three inlets.

    Pick each tool, click the corners or along the run, double-click to finish

    The asphalt lot, the curb lines, the storm pipes and the inlets traced on the grading plan
    Kisheet, October 21, 2026
  6. 6

    Read the totals

    Group the takeoff table by subject and filter out the spot elevations: the cut and fill, the asphalt area, the curb and each pipe by length, and the inlet count.

    Takeoff table › Group by › Subject, then Filter (here in its own window)

    The takeoff table grouped by subject with cut and fill, asphalt, curb, storm pipe and inlets
    Kisheet, October 21, 2026
What you need, and how Kisheet does it

Built for how a sitework bid comes together.

Cut and fill on a PDF

Existing and proposed grade spots read from the printed elevations (EL, FF, TC, INV and plain numbers); cut and fill for any area in cubic yards, with the cells either surface doesn't reach reported.

Cross sections

Trace cut and fill areas on the section sheets and give each a station, such as 12+50: volumes between stations come by average end area.

Strip and import

Area × depth for topsoil. Order in cubic yards with a swell or shrink percent (25 for loose, −10 for compacted), so BCY, LCY and CCY stay labeled.

Paving

Square yards from the area; tons by density (about 2.0 tons per CY for asphalt), set per lift.

Curb, pipe and silt fence

Lengths by type; trace each depth band of a pipe as its own run.

Inlets and structures

Count them, or let Visual Search find every one.

Excel for your bid system

Export by item, ready to map to bid items.

A site tool set, ready on day one

Asphalt surface and binder, aggregate base, concrete paving, curb and gutter, striping, topsoil strip, cut and fill, RCP and HDPE storm, PVC sanitary, manholes, inlets, silt fence, sod and seed.

When you still want a 3D earthwork tool: Kisheet works from the 2D plan and section sheets: no surfaces from contour lines, mass haul or machine-control files. For those you still want a 3D earthwork tool.